For the Renovation and extension of the primary school in Loswaki following constructions were executed:

  • Completion of 2 classrooms for which the village community had laid the foundations years ago
  • Completion of 4 homes for teachers for whom the village community laid the foundation years ago
  • Timeline:

  • Construction phase 1: August 2018 – beginning of 2019
  • Construction phase 2: March – June 2019
  • Handover to the government: August 2019
  • We thank FLY&HELP for the financial support of this project.